Moranbah ammonium nitrate project (Project Aurora)

Client
Incitec Pivot
Sector
Resources
Expertise
  • Engineering design
  • Construction and commissioning
Contract type
Country
Australia
State
Queensland
Location
Moranbah
Status
Completed
Duration
Tags

UGL, as the Project Aurora team along with partners Conneq Infrastructure Services and BGC Contracting, delivered all engineering and construction services for the project, with UGL acting as the principal contractor.

 

The Project scope involved the reconstruction of the ammonia plant alongside a new nitric acid plant, ammonium nitrate solution plant, ammonium nitrate plant, a 10,000tonne storage facility and associated infrastructure utilities.

 

"The construction team achieved more than 1.5 million man-hours without a lost-time injury, which we believe is an industry leading performance”.
Alan Grace, President Global Manufacturing of Incitec Pivot Limited

 

UGL scope of work included:

  • project management
  • construction
  • detailed engineering:
    • civil
    • structural
    • piping and
    • electrical and instrumentation (E&I)

 

UGL has been involved with this project since 2006 as the primary engineering group for the dismantling of the ammonia plant in the USA and its relocation to Queensland and subsequent engineering and construction of the ammonium nitrate production facility began.

 

 

 

Fast facts

  • weight icon
    2,200tonnes

    the amount of structural steelwork  

  • construction icon
    1,000

    pieces of mechanical equipment and vessels

  • pipes icon
    80km

    the length of piping installed at the plant

  • Size of area icon
    280ha

    the size of the site

X